Prefabrication

PROJECT:

Educational facility

DESCRIPTION:

The contractor was concerned that limited on-site storage space on a confined, town centre site could result in materials supply interruptions, disrupting the work flow. BRC was asked to identify a working method to overcome the lack of storage.

SOLUTION:

In order to minimise site storage requirements, we pre-fabricated the beams and columns and also supplied custom-engineered mesh. This ensured that the steel could be off-loaded and craned into position straight away, virtually eliminating the need for site storage.

BENEFITS:

- 50% reduction in site labour costs
- Improved accuracy and Health & Safety benefits.